I agree. My biggest issue was the bathroom and stands project last summer. They really didn't start until mid-June, when they could have started in April and not affected any sports going on. They weren't done until the end of September. I know they had supply problems with the metal and some issues with workers but some of that was self-inflicted with the other bond projects going on. NISD finally got on their case about it and it got done. It looks like they learned some lessons from that and will get the press box started ( and hopefully) done much quicker. Also, I think the press box will be pre-fabricated and then lifted in place so that should save some time. Hopefully the pre-fab is done and its just the site work that needs to be completed before the press box is put in place.